Last Updated 03/16/2010 10:52 AM
This page has approximately the past 30 days worth of updates, see Daily Update Archive page for older updates. More pictures taken by Wor. David Hill here
|
It took two-years and four months of raising money and planning since the June 2006 flood, but on October 29, 2008 the Lodge building was placed back on a new higher concrete foundation and is now out of harms way of being flooded again. By the first week of December we will have complete our Phase I plans, (a new foundation.) We still have a long way to go, we are now ready to start Phase II. But, even after all the planning we had some unforeseen expenses during the Phase I. We are now about $40,000.00 short on funds from being able to bring the Lodge building to a minimal usable state for the purpose of holding stated communications. Although the Lodge building in now on a new foundation and will have completed the concrete access ramp and foundation walls for the bathroom addition, we have come-up sort with being able to build the bathroom addition, much less add bathrooms, well-pump tank, water heater, electric heaters, new HVAC system, or a kitchen. If we are able to acquire $40k more, we can add the bathrooms which will bring the Lodge building to a minimal usable state. As we progress into Phase II repairs and improvements, over the next few weeks and months (now years) we are going to be very dependent on free Masonic Labor to accomplish them. Here are some examples, electrical wiring, installing fiberglass insulation, hanging drywall, installing doors, removing the wall paneling and carpet from the second floor, resize the Masters station and alter, sanding and painting, cleaning, and much more… These projects are in the process of being scheduled, so please be prepared to lend a hand so that we can once again start having meetings in OUR Lodge building
Timeline June 2006 Flooded July 2008 empty Lodge building for repairs.
|
10-04-09 The Grand Master stopped by and made a surprise visited to Acacia. Stucco as been repaired, handrails for access ramp are being installed, backdoor has been installed, more painting has been done, shed has been moved.
10-11-09 front overhang, handrails.